Adams County Board delays decision on disputed Jail bill

Adams County Board delays decision on disputed Jail bill

1 week, 1 day ago by Scott Hardy

Hoping settlement's reached in next month

The Adams County Board has delayed how to proceed in a dispute with a contractor over demolition work on the site of the new County Jail.

The Board Tuesday night tabled for a month a decision on whether to make an additional payment to Blick's Construction Company, who tore down buildings on the County Jail site prior to the start of construction. Jail sub-committee Chair Mark Peter says both sides could still reach an agreement.

( Mark Peter  :10 )

Peter adds that the Company did the work without submitting a change order request to the Board. The Jail sub-committee voted last week to recommend not paying the additional bill.